A T2 application is associated with roadworks having a maximum duration of 30 calendar days on a single road. There is no constraint on distance. 10 days are required for the conditions of work to be finalised at which time a licence to work is issued.
A T2 form is generated as follows:
Enter project specifics such as the number of ducts, length of roadway, footpath, green area and open space affected.
Select the SAVE AS DRAFT button to save the application.
The applicant is issued with a unique T2 reference code ALREAD-T2/2006-MAY/165
Select the SUBMIT button to enter the application and allow the conditioning period to commence.
Select the T2 CHARGES button to display the project charges.
Reinstatement charges are refunded when the works guaranteed period expires.
The initial conditions associated with the project can be viewed by selection of the VIEW CONDITIONS button.